Funding For Study of the North York Bridle Path -
Post Road Drainage System - Ward 9 - North York Centre South.
The North York Community Council recommends the adoption of the following report (January 14, 1998) from the Commissioner of Public Works:
Purpose:
The purpose of this report is to seek funding authorization for a study of an innovative drainage system installed in the Bridle Path - Post Road area as part of the 1997 road reconstruction program.
Funding Source, Financial Implications and Impact Statement:
Water Rate - Sewer and Erosion Capital Account.
Recommendations:
It is recommended that:
(1) the City=s portion of funding a monitoring study of the Bridle Path - Post Road drainage system in the amount of $50,000.00 be financed from the Sewer and Erosion Capital Account (no 1998 operating budget impact);
(2) the Great Lakes 2000 Cleanup Fund and the Ministry of Environment in charge of the Storm Water Assessment Monitoring and Performance Program (SWAMP) be notified;
(3) upon completion of the study, a further report be submitted with the findings and recommendations; and
(4) the appropriate City officials be authorized and directed to take the necessary action to give effect thereto.