BD177.1 | ACTION |
Adopted |
|
|
Contract Awards - July 7, 2010 - Composite Report |
Committee Decision |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
The Bid Committee adopted the following:
1. Bid Committee grant authority to award the following contracts in accordance with the Contract Details set out in the appendices of the report (Jun 30, 2010) from the Director of Purchasing and Materials Management:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Origin |
(June 30, 2010) Report from the Director, Purchasing and Materials Management |
Summary |
The purpose of this report is to advise on the results of the competitive procurement calls issued by the Purchasing and Materials Management Division and to recommend contract awards as outlined in this report. |
Background Information |
Contract Awards - July 7, 2010 - Composite Report (http://www.toronto.ca/legdocs/mmis/2010/bd/bgrd/backgroundfile-31849.pdf) |
Motions |
1 - Motion to Adopt Item (Carried) That the Bid Committee deal with each contract separately, moved by Don Altman. 2 - Motion to Adopt Item (Carried) That the Bid Committee grant authority to award Request for Proposal (RFP) 9118-10-7038, in accordance with the Contract Details set out in the appendices of the report (June 30, 2010) from the Director, Purchasing and Materials Management, moved by John Ricchiuto. 3 - Motion to Adopt Item (Carried) That the Bid Committee grant authority to award Tender Call 120-2010, Contract No. 10EY-08RD, in accordance with the Contract Details set out in the appendices of the report (June 30, 2010) from the Director, Purchasing and Materials Management, moved by Wayne Scott. 4 - Motion to Adopt Item (Carried) That the Bid Committee grant authority to award Tender Call 134-2010, Contract No. 10EY-43WS, in accordance with the Contract Details set out in the appendices of the report (June 30, 2010) from the Director, Purchasing and Materials Management, moved by Wayne Scott. 5 - Motion to Adopt Item (Carried) That the Bid Committee grant authority to award Tender Call 131-2010, Contract No. 10EY-05RD, in accordance with the Contract Details set out in the appendices of the report (June 30, 2010) from the Director, Purchasing and Materials Management, moved by Wayne Scott. 6 - Motion to Adopt Item (Carried) That the Bid Committee grant authority to award Request for Quotation 0203-10-0060, in accordance with the Contract Details set out in the appendices of the report (June 30, 2010) from the Director, Purchasing and Materials Management, moved by Laurie McQueen. 7 - Motion to Adopt Item (Carried) That the Bid Committee grant authority to award RFQ No. 3907-10-5055, in accordance with the Contract Details set out in the appendices of the report (June 30, 2010) from the Director, Purchasing and Materials Management, moved by Mike Major. 8 - Motion to Adopt Item (Carried) That the Bid Committee grant authority to award Request for Proposal (RFP) No. 9150-10-3091, in accordance with the Contract Details set out in the appendices of the report (June 30, 2010) from the Director, Purchasing and Materials Management, moved by Don Altman. 9 - Motion to Adopt Item (Carried) That the Bid Committee grant authority to award Request for Quotation 6113-10-3099, in accordance with the Contract Details set out in the appendices of the report (June 30, 2010) from the Director, Purchasing and Materials Management, moved by Vukadin Lalovic. |
BD177.2 | ACTION |
Adopted |
|
Ward: 36 |
Award of Tender Call No. 68-2010 |
Committee Decision |
The Bid Committee took the following action:
1. Re-opened the award of Tender Call No. 68-2010 which was previously approved at its meeting held on June 9, 2010.
2. Rescinded its decision of June 9, 2010 to award Tender Call No. 68-2010.
3. Granted authority to award Tender Call No. 68-2010, for the supply of all labour, equipment, material and supervision necessary to construct an addition to the Scarborough Village Community Centre, to Rankine Construction Ltd., in accordance with the revised Contract Details set out in Appendix 1 contained in the report (June 30, 2010) from the Director of Purchasing and Materials Management. |
Origin |
(June 30, 2010) Report from the Director, Purchasing and Materials Management |
Summary |
The purpose of this report is to request the Bid Committee to rescind the award of Tender Call No. 68-2010 submitted on June 3, 2010 and approved by the Bid Committee at its meeting of June 9, 2010 in the amount of $1,127,513.00 net of all applicable taxes and charges. This new report is seeking to increase the contract by $54,000.00 bringing the new recommended award to $1,181,513.00 net of all applicable taxes and charges to the same vendor, Rankine Construction Ltd, being the lowest bidder meeting specifications for the supply of all labour, equipment, material and supervision necessary to construct an addition to the Scarborough Village Community Centre.
This error was due the contingency amount being understated by $54,000.00 in the original composite report. This report is now being submitted to correct the error. |
Background Information |
Award of Tender Call No. 68-2010 (http://www.toronto.ca/legdocs/mmis/2010/bd/bgrd/backgroundfile-31850.pdf) |
Motions |
1 - Motion to Re-open Item (Carried) That the Bid Committee re-open the award of Tender Call No. 68-2010 which was previously approved by the Bid Committee on June 9, 2010, moved by Don Altman. 2 - Motion to Adopt Item (Carried) That the Bid Committee adopt the following recommendations contained in the report (June 30, 2010) from the Director, Purchasing and Materials Management, moved by Don Altman:
1. The Bid Committee decision of June 9, 2010 to award Tender Call No. 68-2010, be rescinded.
2. The Bid Committee grant authority to award Tender Call No. 68-2010, for the supply of all labour, equipment, material and supervision necessary to construct an addition to the Scarborough Village Community Centre, to Rankine Construction Ltd., in accordance with the revised Contract Details set out in the Appendix 1 to this report. |
Procedural Motions |
1 - Motion to Adopt Minutes (Carried) Moved by Laurie McQueen That the minutes of the Bid Committee meeting held on June 30, 2010, be confirmed. |
Members Present:
Maria Kolominsky, City Clerk's designate as Chair Laurie McQueen, City Manager's designate Don Altman, Deputy City Manager and Chief Financial Officer's designate John Ricchiuto, Facilities Management (Request for Proposal (RFP) 9118-10-7038) Wayne Scott, Technical Services Division (Tender Call 120-2010, Contract No. 10EY- 08RD; Tender Call 134-2010, Contract No. 10EY-43WS; Tender Call 131-2010, Contract No. 10EY-05RD) Mike Major, Business Improvement Area Office (RFQ No. 3907-10-5055) Vukadin Lalovic, Fleet Services Division (Request for Quotation 6113-10-3099) |
Wednesday, July 7, 2010 |
Meeting Sessions |
Session Date | Session Type | Start Time | End Time | Public or Closed Session |
2010-07-07 | Afternoon | 2:00 PM | 2:10 PM | Public |