Construction on the west side of Port Union Rd, between Island Road and Lawrence Ave East is now complete.  Starting the week of December 2, traffic will shift to the west side to allow winter work to begin on the east side of Port Union Rd. A winter break is scheduled from December 20 to January 5. See the News & Updates and Travel Impacts tabs for more details.

In July 2023, the City of Toronto initiated preliminary work to prepare for the road reconstruction and replacement of the City-owned portion of substandard water service connections on Port Union Road from Island Road to Lawrence Avenue East. Improvements being made as part of this work include widening Port Union Road to create a new northbound vehicle lane, installation of raised cycle tracks and continuous sidewalks on both sides of the street. Full road reconstruction started in spring 2024.

To improve road safety, new centre-lanes will be placed at select locations, and curb extensions with raised pedestrian crossings will be added at side streets.  Once complete, these changes will improve conditions for people walking, cycling and driving, and will help to better manage traffic flow.

November 2024

Construction on the west side of Port Union Road, between Island Road and Lawrence Avenue East is now complete.

Winter work on the east side of Port Union Road

The following work has been identified as the most suitable to carry out during the winter months to ensure steady progress on the project.  All activities are weather-dependent and may need to pause during periods of extreme cold or heavy snowfall.  Planned work includes:

  • Installation of catch basins, starting from Lawrence Avenue East and moving north
  • Installation of streetlighting poles and the required underground conduits
  • Construction of the retaining walls at Blue Anchor Trail (near Dear Gate) and Lawson Road

Snow clearing will be managed by both the contractor and the City’s winter operations team.  There will be a winter break from December 20, 2024, to January 5, 2025.

August 2024

The City of Toronto began road reconstruction on Port Union Road from Island Road to Lawrence Avenue East in July 2023 and was anticipated to be completed in December 2024.  However, due to conflicts with several existing underground utilities, including Bell, Hydro, and Rogers, construction work was delayed while the City’s contractor addressed and resolved these known conflicts.

The City now expects all road work on the west side of Port Union Road from Island Road to Lawrence Avenue East to be completed by mid-December 2024.  To advance the road work, the contractor will be looking to work over the winter months (weather permitting). The contractor will then start work on the east side of Port Union Road in Spring 2025.

The overall project is now projected to be completed by late 2025.

See the Construction Update #3 for more details.

March 2024

December 2023

June 2023

June 2023

  • A virtual Public Information Meeting was held on June 28, 2023 to present an update and provide an opportunity to ask questions about the upcoming construction.  View the Presentation for details.

 

The construction area, illustrated below, is Port Union Road from Lawrence Avenue East to Island Road.

Study area is along Sheppard Avenue East from Island Rd to Lawrence Avenue East

 

Vehicular Traffic Improvements

  • Widening of Port Union Road to allow a new northbound lane
  • Centre-turn lanes and narrower lane widths to improve road safety
  • New asphalt on the roadway
  • Traffic signal updates
  • Speed limit reduction to 50km/hr

Cycling Improvements

  • Raised cycle tracks on both sides of the street

Pedestrian Improvements

  • New and wider sidewalks on both sides of the street
  • Accessible pedestrian crossings with tactile plates
  • Raised crosswalks and corner radii reductions to improve pedestrian safety
  • Formal bus stops with shelters integrated with the design of cycle tracks

Infrastructure Improvements

  • Updated street lighting and hydro poles
  • Replacement of the watermain, if required
  • Upgraded water service connections and stormwater drainage

For further details on the improvements, please see November 2021 Public Information presentation and the roll plan for property specific details.

Timing and Schedule

The project is expected to take from July 2023 to late 2025.

Work Hours

Work can take place from 7 a.m. to 7 p.m., Monday to Friday, with work after hours and on weekends as required.

Noise

The contractor is responsible to minimize construction related noise.  Higher levels of noise can be anticipated during concrete breaking work.

Dust

The contractor is responsible for minimizing dust in the work zone.

Deliveries

The City has been working with businesses and property management representatives to accommodate delivery and loading activities during construction.  If you have not yet discussed your delivery needs with the project team, please contact the staff person listed on this web page as soon as possible.

Accessibility Accommodation

The City’s contractor must ensure safe and accessible walkways and entryways are maintained for everyone during construction.  Any temporary access disruptions will be communicated as soon as possible.  If you experience a disruption, have a specific access need or related accommodation request, contact the person listed on this web page.

If travelling in the area, please be aware:

  • Starting the week of December 2, traffic will shift to the west side of Port Union Road with one lane of traffic in each direction with turning lanes added  to keep traffic moving by preventing delays behind turning vehicles at the following key intersections:
    • Rozell Road, for northbound traffic
    • Lawson Road/Fanfare Avenue, for northbound and southbound traffic
    • Clappison Road for northbound traffic
    • Lawrence Avenue East, for southbound traffic
    • Additional travel lane between Blue Anchor Trail and Island Road
  • The cycle track will remain closed until the completion of the project
  • Pedestrian access along Port Union Road will be maintained at all times

Turning lanes and the additional travel lane will be impacted when work occurs within close proximity to these lanes.  These impacts will be temporary and the lanes will reopen once the work is complete.

TTC Service Impacts

  • TTC bus routes will continue to operate during construction
  • Bus stops may be temporarily relocated, if required
  • Visit ttc.ca for further updates on service

The Environmental Assessment (EA) for this project was approved in 2004. A subsequent EA Addendum (update) was completed in 2014, approved in 2015 and made changes to the original study design in order to reduce property and community impacts.

Original Environmental Study Report (2004)

This Environmental Assessment Study identified a preferred design which included:

  • An additional northbound lane on Port Union Road from Lawrence Avenue East to Island Road
  • A continuous centre left-turn lane on Port Union Road from Winter Gardens Trail to Island Road
  • A landscaped centre median on Port Union Road from Lawrence Avenue East to Winter Gardens Trail
  • Bicycle lanes on both sides of the road from Lawrence Avenue East to Island Road
  • Additional turn lanes at the intersection of Kingston Road and Port Union Road
  • Complete sidewalks on both sides of Port Union Road

Environmental Assessment Addendum (2014)

The Addendum (update) to the 2004 ESR was approved by the Ministry of Environment and Climate Change (MOECC) in August 2015.

In consultation with the community as directed by City Council in 2004, the preferred design was modified to reduce property and other impacts to the community, and to meet current City standards and practices. The updated preferred design provides the same level of service as the original design, but includes the following changes:

  • Length of landscaped median reduced (now between Lawrence Avenue East and Clappison Boulevard only)
  • Section of centre left-turn lane removed south of Josaly Drive
  • Private property no longer required
  • Bike lanes widened from 1.5 metres to 1.8 metres

To view the Environmental Assessment Addendum Report, contact Nathalie Forde at 416-392-3556 or Nathalie.Forde@toronto.ca.

Field Investigations (2017)

The City conducted field investigations including a survey of the area and analysis of soil samples in various locations along Port Union Road to confirm ground conditions. Based on the results, the City is developing the project design.

Detailed Design (2017 – 2021)

The City completed the detailed design, utility relocations and secured easements. In the summer of 2021, the detailed design was updated to accommodate additional safety improvements including a raised cycle track, curb extensions with reduced corner radii, setback raised pedestrian crossings and speed limit reduction to 50km per hour.

Additional Road Safety Measures

In addition, several improvements are included in the design for the project that have the potential to reduce traffic speeds and infiltration into residential areas, including Tilley Drive, and improve visibility of pedestrians and cyclists.  These improvements include:

  • New raised pedestrian crossings, setback from Port Union Road;
  • Reduced curb radii; and
  • Curb extensions

Project Update Meeting (2021)

A Virtual Project Update Meeting was held on November 30, 2021.  Please see Port Union Road Virtual Public Information Event presentation and the Port Union Road roll plan for property specific details.

 

Stay Informed

Sign-up to receive construction updates by email.